| Identity number: | D00025 |
| DCC: | BE |
| Status level: | Standard |
| Name: | Time schedule |
| Content of information: | Description:
Relationship between activities and time-period.
Mandatory content of information:
– Defined activity;
– Division of activities into sub-activities, if required (e.g. preliminary studies, engineering, manufacturing, testing, dispatch, erection, commissioning, etc.);
– Start and end dates for each activity.
Optional content of information:
– Dependencies between activities;
– Critical paths;
– Possible slack time;
– Hold points / witness points. |
| Application area: | Overall management |
| Activity area: | Management - planning and scheduling, Management - process and workflow |
| Form of presentation: | C - Chart or graph, T - Table or list |
| Released on: | 2008-04-14 |
| Applies: | D00001 (X Chart); D00005 (X Table) |
| Keywords: | schedules, time schedules, time tables |
| Source references: | IEC 61355:1997 |
|